The Homestead




Project Milestones

Apr ’15 – Completion date
Mar ’15 – Final finishings applied to build
Feb ’15 – Garage interior finished
Feb ’15 – Cedar cladding on outside of walls
Jan ’15 – Kitchen fit out in progress, walk in wardrobe starting to take shape, Bathrooms tiled
Jan ’15 – Clading  and interiors start to go up, Painting commences
Dec ‘14 – Insulation and airtightness  test. All the hard work proved to be successful as airtight worthiness test passed with flying colours (see article)
Nov ‘14 – Innovative ceiling system installed – new concept that allows for working platform for trades, installed in a day and provides a waterproof lid on the build
Nov ‘14 – Pre built  walls were delivered and erected.  This ensures they are watertight before even arriving on site.
Oct  ‘14 – Work commenced